Toachi - Pilatón, Provincia Santo Domingo de los Sachilas; Cantón Sa, Ecuador

Status: Under construction

0 hectares per MW

0 people per MW

Results

Net Present Value98,534 thousand USD
Hectares flooded per MW0 hectares per MW
Gross CO₂ equivalent emissions10,687 metric tonnes
Gross CO₂ equivalent per MW47 metric tonnes per MW
Hectares flooded per MW0 hectares per MW
People displaced per megawatt0 people per MW

Inputs and assumptions

People displaced0 people displaced
Area flooded34 hectares
Installed capacity 228 MW
Capacity used90%
Construction time4 years
Construction cost420,000,000 USD
Transmission infrastructure cost0 USD
Wholesale price of energy46.9 USD
Economic discount rate10%