Tahuamani, Porvenir Municipality, Pando Department, Bolivia

River: Tahuamani

Status: Proposed project

0 hectares per MW

167 people per MW

Map of Porvenir Municipality, Pando Department, Bolivia
Enable javascript to view charts.

Results

Net Present Value-15,450 thousand USD
NPV including net greenhouse gas emissions-15,196 thousand USD
Cost per MWh excluding environmental costs147 USD per MWh
Hectares flooded per MW0 hectares per MW
Gross CO₂ equivalent emissions5,990 metric tonnes
Gross CO₂ equivalent per MW998 metric tonnes per MW
Hectares flooded per MW0 hectares per MW
People displaced per megawatt167 people per MW

Inputs and assumptions

People displaced1,000 people displaced
Area flooded1 hectare
Vegetation type or land coverTropical Rainforest Forest, Mostly natural
Carbon density193 tC/ha
Installed capacity 6 MW
Capacity used55%
Construction time6 years
Construction cost15,000,000 USD
Transmission infrastructure cost5,000,000 USD
Wholesale price of energy20 USD
Economic discount rate12%