Rondon 2, Rondonia, Brazil

River: Comemoração

Status: In Operation

313 hectares per MW

34 people per MW

Enable javascript to view charts.

Results

Net Present Value270,154 thousand BRL
NPV including net greenhouse gas emissions82,436 thousand BRL
Internal Rate of Return14.3%
Hectares flooded per MW313 hectares per MW
Gross CO₂ equivalent emissions74,083 thousand metric tonnes
Gross CO₂ equivalent per MW1,008 thousand metric tonnes per MW
Hectares flooded per MW313 hectares per MW
People displaced per megawatt34 people per MW

Inputs and assumptions

People displaced2,500 people displaced
Area flooded23,000 hectares
Vegetation type or land coverAmericas; Tropical Rainforest; Forest, Cropland Mosaic; Non-Frontier - 96.5
Carbon density96.50 tC/ha
Installed capacity 73.5 MW
Capacity used40%
Construction time2 years
Construction cost255,900,000 BRL
Transmission infrastructure cost12,795,000 BRL
Wholesale price of energy200 BRL
Economic discount rate7%