HydroCalculator

Miguillas - Umalpaca, Chapare, Cochabamba Department, Bolivia

River: Maguillas

Status: Proposed project

0 hectares per MW

0 people per MW

Map of Chapare, Cochabamba Department, Bolivia
Enable javascript to view charts.

Results

Net Present Value-96,924 thousand USD
NPV including net greenhouse gas emissions-93,877 thousand USD
Cost per MWh excluding environmental costs85 USD per MWh
Hectares flooded per MW0 hectares per MW
Gross CO₂ equivalent emissions5,503 metric tonnes
Gross CO₂ equivalent per MW95 metric tonnes per MW
Hectares flooded per MW0 hectares per MW
People displaced per megawatt0 people per MW

Inputs and assumptions

People displaced0 people displaced
Area flooded2 hectares
Carbon density87 tC/ha
Installed capacity 58 MW
Capacity used60%
Construction time5 years
Construction cost, including transmission infrastructure costs123,000,000 USD
Wholesale price of energy17.62 USD
Economic discount rate12%