Isimanchi II, Zamora-Chinchipe, Ecuador

River: Isianchi

Status: Under construction

0 hectares per MW

0 people per MW

Map of Zamora-Chinchipe, Ecuador
Enable javascript to view charts.

Results

Net Present Value-2,736 thousand USD
NPV including net greenhouse gas emissions-2,554 thousand USD
Internal Rate of Return5.32%
Cost per MWh excluding environmental costs54 USD per MWh
Hectares flooded per MW0 hectares per MW
Gross CO₂ equivalent emissions2,954 metric tonnes
Gross CO₂ equivalent per MW1,284 metric tonnes per MW
Hectares flooded per MW0 hectares per MW
People displaced per megawatt0 people per MW

Inputs and assumptions

People displaced0 people displaced
Area flooded1 hectare
Carbon density87 tC/ha
Installed capacity 2.3 MW
Capacity used85%
Construction time1 year
Construction cost, including transmission infrastructure costs5,257,770 USD
Wholesale price of energy30 USD
Economic discount rate12%