HydroCalculator

Inambari, Madre de Dios, Peru

River: Inambari

Status: Proposed project

17 hectares per MW

2 people per MW

Map of Madre de Dios, Peru
Enable javascript to view charts.

Results

Net Present Value-19,996 million PEN
NPV including net greenhouse gas emissions-20,079 million PEN
Internal Rate of Return2.44%
Cost per MWh excluding environmental costs583 PEN per MWh
Hectares flooded per MW17 hectares per MW
Gross CO₂ equivalent emissions144,696 thousand metric tonnes
Gross CO₂ equivalent per MW65,771 metric tonnes per MW
Hectares flooded per MW17 hectares per MW
People displaced per megawatt2 people per MW

Inputs and assumptions

People displaced4,000 people displaced
Area flooded37,000 hectares
Carbon density126 tC/ha
Installed capacity 2,200 MW
Capacity used60%
Construction time6 years
Construction cost11,297,440,000 PEN
Transmission infrastructure cost23,108,400,000 PEN
Wholesale price of energy157 PEN
Economic discount rate12%