HydroCalculator

Inambari, Inambari, Madre de Dios, Peru

River: Inambari

Status: Proposed project

17 hectares per MW

1 person per MW

Enable javascript to view charts.

Results

Net Present Value926,213 thousand PEN
NPV including net greenhouse gas emissions959,804 thousand PEN
Internal Rate of Return13.3%
Hectares flooded per MW17 hectares per MW
Gross CO₂ equivalent emissions115,857 thousand metric tonnes
Gross CO₂ equivalent per MW52,662 metric tonnes per MW
Hectares flooded per MW17 hectares per MW
People displaced per megawatt1 person per MW

Inputs and assumptions

People displaced2,092 people displaced
Area flooded37,766 hectares
Installed capacity 2,200 MW
Capacity used70%
Construction time5 years
Construction cost4,425,000,000 PEN
Transmission infrastructure cost0 PEN
Wholesale price of energy70 PEN
Economic discount rate11%