HydroCalculator

Coca Codo, Napo; Cantón: El Chaco

River: Coca

Status: Under construction

0 hectares per MW

0 people per MW

Enable javascript to view charts.

Results

Net Present Value-1,206 million USD
NPV including net greenhouse gas emissions-1,142 million USD
Internal Rate of Return3.50%
Cost per MWh excluding environmental costs48 USD per MWh
Hectares flooded per MW0 hectares per MW
Gross CO₂ equivalent emissions46,432 metric tonnes
Gross CO₂ equivalent per MW31 metric tonnes per MW
Hectares flooded per MW0 hectares per MW
People displaced per megawatt0 people per MW

Inputs and assumptions

People displaced0 people displaced
Area flooded34 hectares
Installed capacity 1,500 MW
Capacity used80%
Construction time6 years
Construction cost, including transmission infrastructure costs2,245,000,000 USD
Wholesale price of energy19 USD
Economic discount rate12%

Vegetation & carbon density

Carbon density
(tC/ha)
Area flooded
(hectares)
Total carbon
(tonnes)
1.87.01750%1,479.0
2.1.01750%17.0
Total34100%1,496.0