HydroCalculator

Chorillos, Zamora-Chinchipe, Ecuador

River: Chorillos

Status: Under construction

0 hectares per MW

0 people per MW

Map of Zamora-Chinchipe, Ecuador
Enable javascript to view charts.

Results

Net Present Value-7,655 thousand USD
NPV including net greenhouse gas emissions-7,430 thousand USD
Internal Rate of Return3.60%
Cost per MWh excluding environmental costs97 USD per MWh
Hectares flooded per MW0 hectares per MW
Gross CO₂ equivalent emissions1,535 metric tonnes
Gross CO₂ equivalent per MW384 metric tonnes per MW
Hectares flooded per MW0 hectares per MW
People displaced per megawatt0 people per MW

Inputs and assumptions

People displaced0 people displaced
Area flooded1 hectare
Installed capacity 4 MW
Capacity used67%
Construction time2 years
Construction cost, including transmission infrastructure costs12,461,467 USD
Wholesale price of energy45 USD
Economic discount rate12%

Vegetation & carbon density

Carbon density
(tC/ha)
Area flooded
(hectares)
Total carbon
(tonnes)
1.5.0150%2.5
2.87.0150%43.5
Total1100%46.0