Chacorão, Jacareacanga, Pará

River: Tapajós

Status: Construction Scheduled

18 hectares per MW

0 people per MW

Map of Jacareacanga - Para, Brazil
Enable javascript to view charts.

Results

Net Present Value1,916 million BRL
NPV including net greenhouse gas emissions1,916 million BRL
Internal Rate of Return11.0%
Hectares flooded per MW18 hectares per MW
Gross CO₂ equivalent emissions244,723 thousand metric tonnes
Gross CO₂ equivalent per MW73,358 metric tonnes per MW
Hectares flooded per MW18 hectares per MW
People displaced per megawatt0 people per MW

Inputs and assumptions

People displaced18 people displaced
Area flooded61,600 hectares
Carbon density128 tC/ha
Installed capacity 3,336 MW
Capacity used55%
Construction time6 years
Construction cost8,600,000,000 BRL
Transmission infrastructure cost0 BRL
Wholesale price of energy100 BRL
Economic discount rate10%